前 言·····································································Ⅱ 1 范围···································································1 2 术语和定义·····························································1 3 编制要求 ····························································· 2 4 内容要素······························································ 2 4.1 编制依据····························································· 2 4.2 工程概况····························································· 3 4.3 施工规划 ·····························································3 4.4 施工准备 ·····························································3 4.5 施工方法 ·····························································5 4.6 质量检验 ·····························································5 4.7 安全管理 ·····························································6

I

SZDB/Z 20—2009

前 言

施工方案是保证施工质量、保障施工安全、确保施工进度、控制施工成本、指导施工工艺具体实施的技术性文件。鉴于目前电梯施工方案内容形式各异,编制质量参差不齐,为规范施工方案的编制形式和内容,特制定本指导性技术文件。

本指导性技术文件由深圳市质量技术监督局提出并归口。

本指导性技术文件主要起草单位:深圳市质量技术监督局特种设备安全监察处、深圳市特种设备安全检验研究院、深圳市特种设备行业协会。

本指导性技术文件主要起草人:程学源、刘玉歆、梁广炽、刘佳、汪青根、刘锡奎、林铄众、庄小雄、王定成。

本指导性技术文件为首次发布。 II

SZDB/Z 20—2009

电梯安装改造大修工程施工方案编制规范

1 范围

1.1 本指导性技术文件规定了电梯安装改造大修工程施工方案编制要求和内容要素。 1.2 本指导性技术文件适用于曳引式电梯(含杂物电梯)、液压电梯、自动扶梯、自动人行道等安装、改造、大修工程施工方案的编制。

1.3 编制单位可在本规范基础上结合工程实际增加相应内容。 2 术语和定义

下列术语和定义适用于本标准。

2.1 电梯安装工程

在建筑物或构架内将具有产品质量合格证明的电梯产品装配成整机至交付使用的施工过程。包括吊装、安装、调试、检验、移交等过程。 2.2 电梯改造、大修工程

指按照国务院特种设备监督管理部门关于电梯施工类别划分的规定,对已在政府部门注册的电梯进行更新、调整部件或者改变主要参数的施工过程。 2.3 施工方案

指以电梯安装、改造、大修工程为对象进行施工方法分析,并对施工过程中所需人员、材料、设备、工艺进行详细部署,从而保证质量并实现安全文明施工的具体文件。 2.4 电梯施工单位

在工地或者使用现场进行电梯安装、改造、大修工程施工的单位。 2.5 技术交底

主要针对某个工程的概况、施工内容、施工工艺、质量控制点、安全控制点、验收要求等方面对施工单位、项目负责人或施工人员进行的书面性交底材料。 2.6 成品保护

指成品在施工前、施工时、施工后所进行的必要防护,如防止火、水、污染、坠落、撞击、倒塌等,避免成品遭到破坏。成品不仅指竣工后的整台电梯,也指施工过程中每道工序所安装的电梯部件。 3 编制要求

1 SZDB/Z 20—2009

3.1 编制原则

3.1.1 应符合国家有关法律法规、标准、规范以及技术经济政策的要求。 3.1.2 内容应涵盖施工全过程,并应体现科学性、先进性、针对性和可操作性。 3.1.3 方案应体现安全可靠、保证质量、易于操作、便于施工、确保进度、降低成本。 3.1.4 积极应用新材料、新技术和新工艺。 3.2 文件格式要求

3.2.1 施工方案应装订成册,封面上需标明工程名称、工程地点、施工单位、编制单位、编写人、审核人、批准人和编制、审核、批准的日期。配套工艺文件、标准规范等应分册装订。 3.2.2 施工方案需详细编制一个总目录,列出施工方案及配套文件的名称。 3.3 编制程序

3.3.1施工方案应由具有2年以上电梯施工经验的专业技术人员编制, 编制人员应具有助理工程师或以上职称。

3.3.2 施工方案应由具有3年以上电梯施工经验的专业技术人员审核,审核人员应具有工程师或以上职称。

3.3.3 施工方案须经电梯施工单位技术负责人批准后方可实施。 3.3.4 施工过程中如发现方案需要进行修改,须重新经过审核与批准。 4 内容要素 4.1 编制依据

4.1.1 施工方案应列明施工所依据的有关文件。包括:

a)含有技术条件要求的招标文件或销售、安装、改造、大修合同;

b)与电梯相关的建筑施工图纸及其编号、批准日期。施工图纸包括建筑物电梯布置图、电梯井道图、标明电梯层站标高的图纸等。

4.1.2 施工方案应列明施工所涉及的标准、安全技术规范的名称及其编号。

4.1.3 施工方案应列明施工所涉及的工艺文件的名称、编号、制定单位和实施日期。工艺文件一般包括:

a) 安装工艺手册; b) 调试手册; c) 维修保养手册;

d) 机房布置图、井道布置图; e) 部件安装图; f) 电气图;

g) 液压系统原理图(如有); h) 设备仪器作业指导书; i) 安全手册; j) 检验手册; k) 其它。

4.1.4 施工方案应列明施工单位的资质等级、相关业绩以及具有代表性的工程案例。

SZDB/Z 20—2009 4.2 工程概况

施工方案应对下列情况进行说明:

a)工程基本情况。包括工程名称、工程地点、电梯购买单位或使用单位、施工合同编号、电梯数量、内部编号及改造大修的电梯注册编号、计划开工日期和完工日期;

b)电梯基本参数。包括类型、型号、速度、层站数、额定载重量、提升高度、倾角、梯级宽度、主机和控制柜布置方式及改造前后的参数变化等;

c)井道和机房型式与尺寸; d)工程特殊情况。 4.3 施工规划 4.3.1 组织架构

施工方案应明确工程管理架构,列明项目安全管理责任人和相关人员名单。可采用框图形式表示。 4.3.2 工程目标

施工方案应明确下列目标,并应量化: a) 质量目标;

b) 工期目标。包括总体目标和分段目标,目标应具体分解到每台电梯; c) 文明施工目标。包括奖惩指标;

d) 安全目标。包括人员伤亡事故、火灾事故、卫生事故、机电设备事故等指标; 4.3.3 施工协调管理

施工方案中应列明与相关的建设单位、监理单位、土建施工单位、使用管理单位的联系方式和沟通方法。 4.4 施工准备 4.4.1 工作流程

施工方案应明确施工准备的工作流程。可采用流程图表示。 4.4.2 工作内容

4.4.2.1 施工方案应列明安装工程、改造和大修工程前期准备的工作内容。 4.4.2.1 安装工程:

a) 机房和井道建筑工程勘查验收; b) 现场施工人员安置;

c) 脚手架按相关规范搭设和验收; d) 施工用电架设;

e) 电梯设备到达工地及保管情况; f) 土建总体进度及施工管理情况; g) 现场总包单位施工安全管理要求;

h) 确认具备向政府部门办理电梯施工告知的必要材料。 4.4.2.2 改造和大修工程: a) 确认具备向政府部门办理电梯施工告知的必要材料; b) 使用单位对现场施工时间的特殊要求;

3 SZDB/Z 20—2009

c) 施工对周围环境、设施影响的评估及采取的措施。 4.4.3 技术准备

4.4.3.1 施工方案应包括下列技术准备:

a) 了解国家有关法规和标准的要求;了解相关单位需履行的法律义务,包括购买合格的产品、具有合法的施工资质及施工告知手续的办理等;

b) 熟悉图纸,按电梯的型式、规格准备相应标准、工艺文件、自检规程等; c) 办理施工人员用工手续,备齐相应有效的特种设备作业人员证; d) 备齐施工所需计量、测量器具;

e) 制定质量保证措施。包括材料进场管理措施、工程质量管理控制措施、施工操作管理措施、施工技术资料管理措施等;

f) 制定安全保证措施。包括组织管理措施、临时用电管理措施、井道门洞防坠落安全措施、现场消防管理措施、施工机具管理措施等;

g) 制定文明施工措施。包括环境保护措施、生活卫生管理措施、施工现场卫生管理措施等。

4.4.3.2 施工方案应规定施工单位在施工人员进场前对包括吊装人员在内的所有施工人员进行技术交底,并记录存档。技术交底的主要内容包括:

a) 工程概况; b) 工程目标;

c) 施工技术、材料、机具、人员及作业条件准备; d) 执行工艺; e) 检验标准; f) 成品保护; g) 安全措施; h) 文明施工措施;

i) 本工程具有的特殊工艺或其它施工要求。

4.4.3.3 如果采用井道无脚手架施工代替传统的井道搭设脚手架施工的工艺,施工方案还应有对参与井道内施工的所有人员进行无脚手架施工工艺技术交底的要求。 4.4.4 施工进度计划

4.4.4.1 施工方案应明确工程施工进度计划。

4.4.4.2 施工进度计划的编制应考虑到,应反映从施工准备开始,直到工程移交给用户为止的全部施工过程的施工顺序、施工持续时间、工序相互衔接和穿插的情况,包括工程中每一台电梯的施工时间、进度、完工日期及各电梯工程小组之间的衔接、穿插、平行搭接等关系。 4.4.4.3 施工进度计划应明确施工所需辅助材料名称、数量及其进场时间。 4.4.4.4 应明确施工主要机具名称、数量及使用时间。可用计划表表示。

4.4.4.5 施工进度计划应明确工程各工种配置情况、数量及其进场时间。可用表格表示。 4.4.4.6 施工进度计划应能反映出电梯工程与土建工程进程的配合关系。

4.4.4.7 施工进度计划应明确保证施工进度计划实施的技术、劳动力、材料、机具及管理等各项措施。

SZDB/Z 20—2009 4.5 施工方法

4.5.1 施工方案应明确电梯安装、改造或大修工程的施工工序,可用流程图表示。 4.5.2 工程项目如果存在不同制造厂家生产的不同品牌电梯,或同一制造厂家生产的不同类型的电梯,施工方案应对不同电梯采用的不同施工方法有详细的叙述。 4.5.3 施工方法应涵盖下述内容: 4.5.3.1 安装施工:

a) 设备吊装; b) 设备安装; c) 调试; d) 检验。

4.5.3.2 改造或大修施工方法需涵盖电梯从停止使用到验收检验合格的全过程。 4.5.4 施工方法的表述可采用下列形式之一:

a) 安装、大修应按电梯制造厂家现行的安装、维修工艺文件执行; b) 改造应按施工单位现行的改造工艺文件执行;

c) 按照施工工序,对施工过程中所有设备的安装、改造或大修方法进行表述; d) 工艺文件应说明名称、编制单位、编制日期、批准人及实施日期。

4.5.5 对于不能按照电梯制造厂家安装工艺执行的特殊工序,应制定专项施工措施。如大型主机的吊装措施等。

4.5.6 施工方案应该明确电梯安装、改造或大修各个阶段所需具备的作业条件。 4.6 质量检验

4.6.1 施工方案应明确质量检验应该涵盖施工过程中的各个环节。 4.6.1.1 电梯安装工程:

a) 井道土建工程验收; b) 脚手架验收; c) 安装过程检验; d) 关键工序检验; e) 完工自检; f) 调试; g) 交接验收; h) 政府监督检验。 4.6.1.2 改造或大修工程:

a) 脚手架验收;(需要搭设井道脚手架的); b) 更换或者增加部件的安全性能、功能的检验; c) 调试前自检; d) 调试; e) 交接验收; f) 政府监督检验。

4.6.2 施工方案应明确工程执行的检验要求、架构以及组织形式。

5 SZDB/Z 20—2009

4.6.3 施工方案应明确工程中各项检验执行的检验标准、方法以及实施检验的单位、部门。 4.6.4 工程项目如果存在不同制造厂家生产的不同品牌电梯,或同一制造厂家生产的不同类型的电梯,施工方案均需对不同电梯采用的不同检验方法有详细的叙述。 4.7 安全管理

4.7.1 施工方案应明确工程的安全管理组织架构、管理职责及该工程的安全管理直接责任人和安全检查人。

4.7.2 施工方案应明确采用的各种安全措施,消除人的不安全行为、设备的不安全状态和环境的不安全因素。

4.7.3 施工方案应明确施工人员应遵守的各项规章制度。 4.7.4 施工方案应明确从事施工活动时应遵守的安全操作规程。

第二篇:电梯验收规范

1 主题内容与适用范围本标准规定了电梯安装的验收条件、检验项目、检验要求和验收规则。本标准适用于额定速度不大于2.5m/s的乘客电梯、载货电梯,不适用于液压电梯、杂物电梯。

2 引用标准GB 7588 电梯制造与安装安全规范GB 8903 电梯用钢丝绳GB 10058 电梯技术条件GB 10059 电梯试验方法GB 12974 交流电梯电动机通用技术条件 安装验收条件

3.验收电梯的工作条件应符合GB 10058的规定。提交验收的电梯应具备完整的资料和文件。制造企业应提供的资料和文件:装箱单;产品出厂合格证;机房井道布置图;使用维护说明书应含电梯润滑汇总图表和电梯功能表动力电路和安全电路的电气线路示意图及符号说明;电气敷线图;部件安装图;安装说明书

第三篇:电梯安装验收规范

电梯安装验收规范(1) 本标准规定电梯安装的验收条件,检验项目,检验要求和验收规则。

本标准适用与额定速度不大于2.5m/s的乘客电梯,载货电梯,不适用于液压电梯,杂物电梯.

2.引用标准

GB7588 电梯制造与安装安全范围 GB8903 电梯用钢丝绳 GB10058 电梯技术条件 GB10059 电梯实验方法

GB12974 交流电梯电机通用技术条件 3.安装验条件

3.1验收电梯的工作条件应符合GB10058的规定 3.2提交验收的电梯应具备完整的资料和文件. 3.2.1制造企业应提供的资料和文件: a.装箱单

b.产品出厂合格证; c.机房井道布置图;

d.使用维护说明书(应含电梯润滑汇总图表和电梯功能表); e.动力电路和安全电路的电器线路示意图及符号说明; f.电器敷线图; g.部件安装图; h.安装说明书;

i.安全部件:门锁装置.限速器.安全钳及缓冲器式实验报告结论副本,其中限速器与渐进式安全钳还须有调试证书副本.

3.2.2安装企业应提供的资料和文件: a..安装自检记录;

b.安装过程中事故记录与处理报告;

c,由电梯使用单位提出的经制造企业同意的变更设计的证明文件.

3.3安装完毕的饿电梯及其环境应清理干净.机房门窗应防风雨,并标有”机房重地,闲人免进:字样.通向机房的通道应畅通,安全,底坑应无杂物,积水与油污.机房,井道与底坑均不应有与电梯无关的其它设置.

3.4电梯各机械活动部位应按说明书要求加注润滑油.各安全装置齐全,位置正,功能有效,能可靠的保证电梯安全运行.

3.5电梯验收人员必须熟悉所验收的电梯产品和本标准规定的验收方法和要求.

3.6验收用检验器具与实验荷应符合CB10059规定的精度要求,并均周期计量检定周期内. 4.检验项目几检验要求 4.1机房

4.1.1每台电梯应单设有一个切断该电梯电源开关,开关位置应能从机房入口处方便迅速地接近,如几台电梯共用同一机房,个台电梯主电源开关应易于识别.其容量应能切断电梯正常使用情况下的最大电流,但该开关不应切断下列供电电路: a.轿厢照明和通风; b.机房和滑轮间照明; c.机房内电源插座

d.矫定与底坑的电源插座; e.电梯井道照明 f.报警装置.

4.1.2每台电梯应配备供电系统断相,错相保护装置,该装置在电梯运行中断相也应起保护作用.

4.1.3电梯动力与控制线路应分离敷设,从进机房电源起零线和接地线应始终分开,接地线的颜色为黄绿双色缘电线,除36V以下安全电压直接接至地线柱上,不得互相传接后再接地.

4.1.4线管,线槽的敷设应平直,整齐,牢固.线槽内导线总面积不大于槽净面积

60%;线管内导线总面积不大于管内净面积40%;软管固定间距不大于1m,端头固定间距不大于0.1m.

4.1.5控制柜,屏的安装位置应符合:

a.控制柜,屏正面距门,窗不小于600mm; b.控制柜,屏的维修侧距墙不小于600mm; c.控制柜,屏距机械设备不小于500mm. 4.1.6机房内钢丝绳与楼板空洞每边间隙均应为20~40mm,通向井道的孔洞四周应筑一高500mm以上的台阶.

4.1.7 机承重梁饿需埋入承重墙内,则支撑长度应超过墙后中心20mm,且不应小于75mm. 4.1.8 在电机后飞轮上应有与轿厢升降方向相对应的标志.曳引轮.飞轮.限速器轮外侧面应漆成黄色.制动器手动闸扳手漆成红色,并挂在易接近的墙上.

4.1.9 曳引机应有适量润滑油.油标应齐全,有5位显示应清晰,限速器各活动润滑部位也应有可靠润滑.

4.1.10 制动器动作灵活,制动是两侧闸瓦应紧密,均匀地贴合在制动的饿工作面上,松闸时应同步离开,其四角处间隙平均两侧不大于0.7mm 4.1.11 限速器绳轮,选层器钢带轮对垂线的偏差均不大于0.5mm.曳引轮,导向轮对铅垂线的偏差在空载或满载工况下均不大于2mm. 4.1.12 限速器运转应平稳,出厂室动作速度整定封记应完好无拆动痕迹,限速器安装位置正确,底座牢固,当与安全钳联动时无颤动现象.

4.1.13 停电或电气系统发生故障时应有轿厢慢速移动措施,如用手动紧急操作装置,应能用松闸扳手松开制动器,并需用一个持续力去保持其松开状态 4.2井道

4,2,1每根导轨至少应有2个导轨支架,其间距不大于2.5m,特殊情况,应有措施保证导轨安装满足GB7588规定的弯曲强度要求。导轨支架水平度不大于1.5%,导轨支架的地脚螺栓或支架直接埋入深度不应小于120mm.如果用焊接支架其焊缝应是连续的,并应双面焊牢.

4.2.2当电梯冲顶时,导靴不应越出导轨.

4.2.3每列导轨工作面(包括侧面与顶面)对安装基准线没5m的偏差均应不大于下列数值:轿厢导轨设有安全钳的对中重导轨为0.6mm;不设安全钳的T型对重导轨的1.0mm 在有安装基准线时,每列导轨应相对基准线整列检测,取最大偏差值.电梯安装完成后检验导轨时,可对每5m铅垂线分段连续检测(至少测3次),取测量值的相对最大偏差应不大于上述规定值的2倍。

4.2.4轿厢导轨和设有安全钳的对重导轨工作面接头处不应有连续缝隙,且局部缝隙不大于)o.5mm.导轨接头处台阶用直线度为0.01/300的平直尺或其它工具测量,应不大于0.5mm,如超过应修平.修光长度为150mm以上,不设安全钳的对重导轨接头处缝隙不得大于1mm,导轨工作面接头处台阶应不大于0.15mm,如超差亦应校正。 4.2.5两列导轨顶面间的距离批偏差:轿厢导轨为+20 mm ,对重志轨为+30 mm 4.2.6导轨应用压板固定在导轨架上,不应采用焊接或螺栓直接连接.

4.2.7轿厢导轨于设有安全钳的对重导轨的下端应只承在地面坚固的导轨座上.

4.2.8对重块应可靠坚固,对重架若有反绳轮时其反绳轮应润滑良好,并应设有当绳装置. 4.2.9限速器钢丝绳至导轨导向面与顶面二个方向的偏差均不得超过10mm 4.2.10轿厢与对中间的最小距离为50mm,限速器钢丝绳和选层器钢带应张紧,在运行中不得于轿厢后对重相碰触.

4.2.11当对重完全压缩缓冲器时的轿顶空间应满足:

a.井道顶的最低部件与固定在轿顶上设备的最高部件间的距离(不包括导靴或滚轮钢丝绳附件和垂直滑动门的横梁后部件最高部分)与电梯的额定速度V(单位:m/s")有关,其值应不小于,(0.3+0.035V2)m b. 轿顶上方应有一个不小于05m 0.6m 0.8m的矩形空间(可以任何面朝下放置),钢丝绳中心线距矩形体至少一个铅垂面距离不超过0.15m,包括钢丝绳的连接装置可包括这个空间里.

4.2.12封闭式井道内应设置照明,井道最高与最低0.5m内各装一灯外,中间灯距不超过7m. 4.2.13电缆支架的安装应满足:

a.避免随行电缆与限速器钢丝绳,选层器钢带,限位极限等开关,井道传感器及对重装置等交叉;

b. 保证随行电缆在运动中不得与电线槽,管发生卡阻;

c. 轿底电缆支架井道电缆支架平行,并使电梯电缆处于井道底部时能避开缓冲器,并保持一定距离.

4.2..14电缆安装应满足: a.随行电缆两端应可靠固定;

b. 轿厢压缩缓冲器后,电缆不的得与底坑地面和轿厢底边框接触; c. 随行电缆不应有打结和波浪扭曲现象. 4.3 轿厢

4.3.1轿厢顶有反绳轮时,反绳轮应有保护罩和当绳装置,且润滑良好,反绳轮铅垂度不大于1mm 4.3.2轿厢底盘平面的水平度应不超过3/1000 4.3.3 曳引绳头组合应安全可靠,并使每根引绳受力相近,其张力与平均值偏差均不大于5%,且每个绳头锁紧螺母均应安装有锁紧销.

4.3.4 曳引绳应符合GB8930规定,曳引绳表面应清洁不粘有杂质,并宜涂有薄而均匀的ET极压稀释型钢丝绳脂.

4.3.5轿内造操作按钮动作应灵活,信号应显示清晰,轿厢超载装置或称量装置应动作可靠. 4.3.6轿顶应有停止电梯运行的饿非自动复位的红色停止开关,且动作可靠,在轿定检修接通后轿内检修开关应失效

4.3.7轿厢架上若安装有限位开关碰铁时,相对铅垂线最大偏差不超过3mm 4.3.8各种安全保护开关应可靠固定,但不能使用焊接固定,安装后不得因电梯运行正常运行的碰撞后应钢丝绳,钢带,皮带的正常摆动使开关产生位移.损坏和误动作

电梯安装验收规范(2) 4.4 层站

4,.4.1层站指示信号及按钮应符合图纸规定,位置正确 指示信号清晰明亮,按钮动作准确无误,消防开关工作可靠.

4.4.2层门地坎应具有足够的强度,水平度不大于2/1000,地坎应高出装修地面2~~~~5mm 4.4.3层门地坎至轿门地坎水平距离偏差为+30 mm 4.4.4层门门扇与门扇,门扇与门套,门扇下端与地坎的间隙,乘客电梯应为1~6mm载货电梯应为1~~8mm 4.4.5门刀与层门地坎,门锁滚轮与轿厢地坎间隙应为5~~10mm 4.4.6在关门行程1/3之后,阻止关门的力不超过150N 4.4.7层门锁钩,锁臂及动接点动作灵活,在电器安全装置动作之前,锁紧元件的最小齿合长度为7mm 4.4.8层门外观应平整,光洁,无划伤或碰伤痕迹.

4.4.9由轿门自动驱动层门情况下,当轿厢在开锁区域以外时,无论层门由于任何原因而被开启,都应有一种装置能确保层门自动关闭. 4.5底坑

4.5.1轿厢在两端站平层位置时,轿厢,对重装置的撞板与缓冲器顶面间的距离,耗能型缓冲器为150~~400mm,蓄能型缓冲器应为200~~350,轿厢,对重装置的撞板中心与缓冲器中心的偏差不大于20mm. 4.5.2同一基础上的两个缓冲器顶部与轿底对应距离差不大于2mm 4.5.3 液压缓冲器柱塞铅垂度不大于0.5%,充液量正确.且应设有在缓冲器动作后未恢复到正常位置时使电梯不能正常运行的电气安全开关.

4.5.4底坑应设有停止电梯运行的非自动复位的红色停止开关.

4.5.5当轿厢完全压缩在缓冲器上时,轿底最低部分与底坑底之间净空间距离不小于0.5m,且底部应有一个不小于0.5m 0.6m 1.0m的矩形空间(可以任何面朝下放置). 4.6整机功能检验 4.6.1 曳引检查

a.在电源电压波动不大于2%工况下,用逐渐加载测定轿厢上.下行至与重同一水平位置的电流或电压测量法,检验电梯平衡系数应以40%~~50%,测量表必须符合电机供电的频率,电流,电压范围.

b.电梯在行程上部范围内空载上行及行程下部范围125%额定载荷下行,分别听层3次以上,轿厢应被可靠地制停(下行不考核平层要求),在125%额定载荷以正常运行速度下行时,切断电动机与制动器供电,轿厢应被可靠制动.

c.当对重支承在被其压缩的缓冲器上时,空载轿厢不能被曳引绳提升起. d.当轿厢面积不能限制载荷超过额定值时,空载轿厢不能被曳引绳提升起. e.当轿厢面积不能限制载荷过额定值时,在需用150%额定载荷做 引静载检查,历时10min, 引绳无打滑现象.

a.额定速度大于0.63m/s及轿厢装有数套安全钳时应采用渐进式安全钳,其余可采用瞬时式安全钳;

b.限速器与安全钳电器开关在联动实验中动作应可靠,且使曳引机立即制动;

c.对瞬时式安全钳,轿厢应载有均匀分布的额定载荷,短接限速器与安全钳电器开关,轿内无人.并在机房操作下行检修速度是,人为让限速器动作.

对渐进式安全钳,轿厢应载有均匀分布的125%额定载荷,短接限速器与安全钳电气开关,轿内无人.并在机房操作下行检修速度时下行,人为让限速器动作.

以上实验轿厢应可靠制动,切在载荷实验后相对与原正常位置轿厢底倾斜度不超过5% 4.6.3缓冲实验 a.蓄能型缓冲器仅适用于额定速度小于1m/s的电梯,耗能型缓冲器可适用于各种速度的电梯.

b.对耗能型缓冲器需进行复位实验,即轿厢在空载的情况下以检修速度下降缓冲器全压缩,从轿厢开始离开缓冲器,直到缓冲器恢复到原状,所需时间应不大于120 4.6.4层门与轿门轿门联锁实验

a.在正常运行的轿厢未停止在开锁区域内,层门应不能打开;

b.如果一个层门和轿门(在多扇门中任何一扇门)打开,电梯应不能正常启动或继续正常运行

4.6.5 上下极限动作实验

设在井道上下两端的极限位置保护开关,它应在轿厢或对重接触缓冲器前起作用,并在缓冲器前起作用,并在缓冲器被压缩期间动作状态. 4.6.6 安全开关动作实验

电梯以检修速度上下运行时,人为运作下列开关2次,电梯均应立即停止运行. a.安全窗开关,用打开安全窗实验(如设有安全窗); b.轿顶、底坑的紧急停止开关; c.限速器松绳开关。 4.6.7 运行实验

a.轿厢分别以空载、50%额定载荷和额定载荷三种工况,并在通电持续率40%情况下,到达全行程范围,按120次/h,每天不少于8 h,,各起,制动运行1000次,电梯应运行平稳,制动可靠,连续运行无故障.

b.制动器温升不应超过60K,曳引机减速器油温升不超过60K,其温度不应超过 85℃,电动机温升不超过GB12974的规定

c.曳引机减速器,除蜗杆轴伸出一端渗漏油面积平均每小时不超过150cm的平方外,其余各处不得有渗漏油. 4.6.8 超载运行实验

断开超载控制电路,电梯在110%的额定载荷,通电持续率40%的情况下,到达全行程范围.起,制动运行30次,电梯应能可靠的起动,运行和停止(平层不计),曳引机工作正常. 4.7整机性能实验

4.7.1乘客与病床电梯的机房噪声,轿厢内运行噪声与层,轿门开关过程的噪声应符合GB10085规定要求,

4.7.2平层准确应符合GB10085规定要求.

4.7.3整机其他性能宜符合GB10085有关规定要求.

5 验收规则

5.1检验按表1规定项目进行. 5.2判断规则

5.2.1开关层,轿门噪声,平层准确按GB10085规定判定.

5.2.2凡重要项目中任一项不合格,或一般项目中超过8项,均判定为不合格.如果重要项目均合格,一般项目中不合格不超过8项,调整修复,并对原不合格项目及相关项目给予补检.凡最终重要项目全部合格,一般项目不合格不超过3项判定为各,准予验收.判定安全不合格的电梯需全面修复,修复后再次报请验收

5.3交付检验验收合格后,参加验收的各方代表在附录A(参考件)”电梯安装验收证书”上盖章后,方能生效.

电梯安装验收规范(3)

电梯安装验收项目分类表 检验项目 -----机房----- 4.1.1条主电源开关要求 ☆ 2 4.1.2条断,错相保护装置 ☆ 3 4.1.3条敷线与接地要求 4 4.1.4条线管,槽敷设要求 5 4.1.5条控制柜,屏安装位置 6 4.1.6条楼板钢丝绳洞口要求 7 4.1.7条曳引机承重梁要求 8 4.1.8条旋转轮等涂色标记 9 4.1.9条旋转部件润滑要求 10 4.1.10条制动器松,合闸要求 11 4.1.11条绳,带轮铅垂度要求 12 4.1.12条限速器运转等要求 ☆ 13 4.1.13条停电或故障应急措施 ☆ 14 --------井道-------- 4.2.1条导轨安装要求 15 4.2.2条导轨上端位置要求 16 4.2.3条导轨侧工作面直线度 17 4.2.4条导轨接头要求 18 4.2.5条导轨顶面间距 19 4.2.6条导轨固定要求 20 4.2.7条导轨下端支承地面要求 21 4.2.8条对重装置要求 22 4.2.9条限速器绳至导轨面偏差 23 4.2.10条轿厢与对重距离等要求 24 4.2.11条轿顶最小空间要求 ☆ 25 4.2.12条井道照明 26 4.2.13条电缆支架安装要求 27 4.2.14条电缆安装要求 28 --------轿厢-------- 4.3.1条轿顶反绳轮要求 29 4.3.2条轿顶水平度 30 4.3.3条曳引绳头组合等要求 31 4.3.曳引绳要求 32 4.3.5条轿内操纵要求 33 4.3.6条轿顶停止开关 34 4.3.7条安全架限位碰铁安全要求 35 4.3.8条安全保护开关安装要求 36 4.4.1条层站指示要求 37 4.4.2条层们地坎要求 38 -----------层站--------------- 4.4.3条层,轿门地坎间距 39 4.4.4.条层门与地坎间隙 40 4.4.5条门刀与层门等间隙 41 4.4.6条门阻止力 42 4.4.7条门锁要求 43 4.4.8条层门外观要求 44 4.4.9条层门自动关闭装置 45 ---------底坑----------- 4.5.1条轿底与缓冲器等间距 46 4.5.2条缓冲器顶面水平高差 47 4.5.3条缓冲器柱塞铅垂度 48 4.5.4条底坑停止开关要求 49 4.5.5条轿底最小间距与空间 50 整机功能 4.6.1条曳引及平衡系数检查 51 4.6.2条限速器,安全铅联动实验 ☆ 52 4.6.3条缓冲实验 ☆ 53 4.6.4条层门与轿门联锁实验 ☆ 54 4.6.5条上,下极限动作实验 ☆ 55 4.66条安全开关动作实验 ☆ 56 4.6.7条运行实验 ☆ 57 4.6.8条超载运行实验 58 47.1条噪声限值要求检验 59 4.7.2条平层准确度检验

(注:表中打☆为重要项目,其余为一般项目)

第四篇:电梯安装验收规范

1 主题内容与适用范围

本标准规定了电梯安装的验收条件、检验项目、检验要求和验收规则。

本标准适用于额定速度不大于2.5m/s的乘客电梯、载货电梯,不适用于液压电梯、杂物电梯。

2 引用标准

GB 7588 电梯制造与安装安全规范

GB 8903 电梯用钢丝绳

GB 10058 电梯技术条件

GB 10059 电梯试验方法

GB 12974 交流电梯电动机通用技术条件

GB/T10060-2011 电梯安装验收规范

3 安装验收条件

3.1 验收电梯的工作条件应符合GB 10058的规定。 3.2 提交验收的电梯应具备完整的资料和文件。 3.2.1 制造企业提供的资料和文件:

a.

装箱单;

b.

产品出厂合格证;

c.

机房井道布置图;

d.

使用维护说明书(应含电梯润滑汇总图表和电梯功能表);

e.

动力电路和安全电路的电气线路示意图及符号说明;

f.

电气敷线图;

g.

部件安装图;

h.

安装说明书;

i 安全部件:门锁装置、限速器、安全钳及缓冲器型式试验报告结论副本,其中限速器与渐进式安全钳还须有调试证书副本。

3.2.2 安装企业应提供的资料和文件:

a.

安装自检记录;

b.

安装过程中事故记录与处理报告;

c.

由电梯使用单位提出的经制造企业同意的变更设计的证明文件。 3.3

安装完毕的电梯及其环境应清理干净。机房门窗应防风雨,并标有“机房重地,闲人免进”字样。通向机房的通道应畅通、安全,底坑应无杂物、积水与油污。机房、井道与底坑均不应有与电梯无关的其他设置。

3.4 电梯各机械活动部位应按说明书要求加注润滑油。各安全装置安装齐全、位置正确,功能有效,能可靠的保证电梯安全运行。

3.5 电梯验收人员必须熟悉所验收的电梯产品和本标准规定的检验方法和要求。

3.6 验收用检验器具与试验载荷应符合GB 10059规定的精度要求,并均在计量检定周期内。

4 检验项目及检验要求 4.1 机房 4.1.1

每台电梯应单设有一个切断该电梯的主电源开关,该开关位置应能从机房入口处方便迅速地接近,如几台电梯共用同一机房,各台电梯主电源开关应易于识别。其容量应能切断电梯正常使用情况下的最大电流,但该开关不应切断下列供电电路:

a.

轿厢照明和通风;

b.

机房和滑轮间照明;

c.

机房内电源插座;

d.

轿顶与底坑的电源插座;

e.

电梯井道照明;

f.

报警装置。

4.1.2 每台电梯应配备供电系统断相、错相保护装置,该装置在电梯运行中断相也应起保护作用。 4.1.3

电梯动力与控制线路应分离敷设,从进机房电源起零线和接地线应始终分开,接地线的颜色为黄绿双色绝缘电线,除36V以下安全电压外的电气设备金属罩壳均应设有易于识别的接地端,且应有良好的接地。接地线应分别直接接至接地线柱上,不得互相串接后再接地。 4.1.4

线管、线槽的敷设应平直、整齐、牢固。线槽内导线总面积不大于槽净面积60%;线管内导线总面积不大于管内净面积40%;软管固定间距不大于1m,端头固定间距不大于0.1 m。

4.1.5 控制柜、屏的安装位置应符合:

a.

控制柜、屏正面距门、窗不小于600mm;

b.

控制柜、屏的维修侧距墙不小于600mm;

c.

控制柜、屏距机械设备不小于500mm。

4.1.6 机房内钢丝绳与楼板孔洞每边间隙均应为20~40mm,通向井道的孔洞四周应筑一高50mm以上的台阶。

4.1.7 曳引机承重梁如需埋入承重墙内,则支承长度应超过墙厚中心20mm,且不应小于75mm。

4.1.8 在电动机或飞轮上应有与轿厢升降方向相对应的标志。曳引轮、飞轮、限速器轮外侧面应漆成黄色。制动器手动松闸扳手漆成红色,并挂在易接近的墙上。

4.1.9 曳引机应有适量润滑油。油标应齐全,油位显示应清晰,限速器各活动润滑部位也应有可靠润滑。 4.1.10 制动器动作灵活,制动时两侧闸瓦应紧密、均匀地贴合在制动轮的工作面上,松闸时应同步离开,其四角处间隙平均值两侧各不大于0.7mm。

4.1.11 限速器绳轮、选层器钢带轮对铅垂线的偏差均不大于0.5mm,曳引轮、导向轮对铅垂线的偏差在空载或满载工况下均不大于2mm。

4.1.12 限速器运转应平稳、出厂时动作速度整定封记应完好无拆动痕迹,限速器安装位置正确、底座牢固,当与安全钳联动时无颤动现象。

4.1.13 停电或电气系统发生故障时应有轿厢慢速移动措施,如用手动紧急操作装置,应能用松闸扳手松开制动器,并需用一个持续力去保持其松开状态。 4.2 井道

4.2.1 每根导轨至少应有2个导轨支架,其间距不大于2.5m,特殊情况,应有措施保证导轨安装满足GB 7588规定的弯曲强度要求。导轨支架水平度不大于1.5%,导轨支架的地脚螺栓或支架直接埋入墙的埋入深度不应小于120mm。如果用焊接支架其焊缝应是连续的,并应双面焊牢。 4.2.2 当电梯冲顶时,导靴不应越出导轨。 4.2.3

每列导轨工作面(包括侧面与顶面)对安装基准线每5m的偏差均应不大于下列数值:轿厢导轨和设有安全钳的对重导轨为0.6mm;不设安全钳的T型对重导轨为1.0mm。

在有安装基准线时,每列导轨应相对基准线整列检测,取最大偏差值。电梯安装完成后检验导轨时,可对每5 m铅垂线分段连续检测(至少测3次),取测量值间的相对最大偏差应不大于上述规定值的2倍。 4.2.4

轿厢导轨和设有安全钳的对重导轨工作面接头处不应有连续缝隙,且局部缝隙不大于0.5mm,导轨接头处台阶用直线度为0.01/300的平直尺或其他工具测量,应不大于0.05mm,如超过应修平,修光长度为150mm以上,不设安全钳的对重导轨接头处缝隙不得大于1 mm,导轨工作面接头处台阶应不大于0.15mm,如超差亦应校正。 4.2.5 两列导轨顶面间的距离偏差:

轿厢导轨为 mm,对重导轨为 mm。

4.2.6 导轨应用压板固定在导轨架上,不应采用焊接或螺栓直接连接。

4.2.7 轿厢导轨与设有安全钳的对重导轨的下端应支承在地面坚固的导轨座上。

4.2.8 对重块应可靠紧固,对重架若有反绳轮时其反绳轮应润滑良好,并应设有挡绳装置。 4.2.9 限速器钢丝绳至导轨导向面与顶面二个方向的偏差均不得超过10mm。

4.2.10 轿厢与对重间的最小距离为50mm,限速器钢丝绳和选层器钢带应张紧,在运行中不得与轿厢或对重相碰触。

4.2.11 当对重完全压缩缓冲器时的轿顶空间应满足;

a.

井道顶的最低部件与固定在轿顶上设备的最高部件间的距离(不包括导靴或滚轮,钢丝绳附件和垂直滑动门的横梁或部件最高部分)与电梯的额定速度V(单位:m/s)有关,其值应不小于(0.3+0.035 V2)m。

b.

轿顶上方应有一个不小于0.5m×0.6m×0.8m的矩形空间(可以任何面朝下放置),钢丝绳中心线距矩形体至少一个铅垂面距离不超过0.15m,包括钢丝绳的连接装置可包括在这个空间里。

4.2.12 封闭式井道内应设置照明,井道最高与最低0.5m以内各装设一灯外,中间灯距不超过7m。 4.2.13 电缆支架的安装应满足:

a.

避免随行电缆与限速器钢丝绳、选层器钢带、限位极限等开关、井道传感器及对重装置等交叉;

b.

保证随行电缆在运动中不得与电线槽、管发生卡阻;

c.

轿底电缆支架应与井道电缆支架平行,并使电梯电缆处于井道底部时能避开缓冲器,并保持一定距离。

4.2.14 电缆安装应满足:

a.

随行电缆两端应可靠固定;

b.

轿厢压缩缓冲器后,电缆不得与底坑地面和轿厢底边框接触;

c.

随行电缆不应有打结和波浪扭曲现象。 4.3 轿厢

4.3.1 轿厢顶有反绳轮时,反绳轮应有保护罩和挡绳装置,且润滑良好,反绳轮铅垂度不大于1 mm。 4.3.2 轿厢底盘平面的水平度应不超过3/1 000。

4.3.3 曳引绳头组合应安全可靠,并使每根曳引绳受力相近,其张力与平均值偏差均不大于5%,且每个绳头锁紧螺母均应安装有锁紧销。

4.3.4 曳引绳应符合GB 8903规定,曳引绳表面应清洁不粘有杂质,并宜涂有薄而均匀的ET极压稀释型钢丝绳脂。

4.3.5 轿内操纵按钮动作应灵活,信号应显示清晰,轿厢超载装置或称量装置应动作可靠。

4.3.6 轿顶应有停止电梯运行的非自动复位的红色停止开关,且动作可靠,在轿顶检修接通后,轿内检修开关应失效。

4.3.7 轿厢架上若安装有限位开关碰铁时,相对铅垂线最大偏差不超过3mm。

4.3.8 各种安全保护开关应可靠固定,但不得使用焊接固定,安装后不得因电梯正常运行的碰撞或因钢丝绳、钢带、皮带的正常摆动使开关产生位移、损坏和误动作。 4.4 层站

4.4.1 层站指示信号及按钮安装应符合图纸规定,位置正确,指示信号清晰明亮,按钮动作准确无误,消防开关工作可靠。

4.4.2 层门地坎应具有足够的强度,水平度不大于2/1 000,地坎应高出装修地面2~5mm。 4.4.3 层门地坎至轿门地坎水平距离偏差为 mm。

4.4.4 层门门扇与门扇,门扇与门套,门扇下端与地坎的间隙,乘客电梯应为1~6mm,载货电梯应为1~8 mm。

4.4.5 门刀与层门地坎,门锁滚轮与轿厢地坎间隙应为5~10mm。 4.4.6 在关门行程1/3之后,阻止关门的力不超过150N。

4.4.7 层门锁钩、锁臂及动接点动作灵活,在电气安全装置动作之前,锁紧元件的最小啮合长度为7 mm。 4.4.8 层门外观应平整、光洁、无划伤或碰伤痕迹。

4.4.9 由轿门自动驱动层门情况下,当轿厢在开锁区域以外时,无论层门由于任何原因而被开启,都应有一种装置能确保层门自动关闭。 4.5 底坑 4.5.1

轿厢在两端站平层位置时,轿厢、对重装置的撞板与缓冲器顶面间的距离,耗能型缓冲器应为150~400mm,蓄能型缓冲器应为200~350mm,轿厢、对重装置的撞板中心与缓冲器中心的偏差不大于20 mm。

4.5.2 同一基础上的两个缓冲器顶部与轿底对应距离差不大于2mm。

4.5.3 液压缓冲器柱塞铅垂度不大于0.5%,充液量正确。且应设有在缓冲器动作后未恢复到正常位置时使电梯不能正常运行的电气安全开关。

4.5.4 底坑应设有停止电梯运行的非自动复位的红色停止开关。

4.5.5 当轿厢完全压缩在缓冲器上时,轿厢最低部分与底坑底之间的净空间距离不小于0.5 m,且底部应有一个不小于0.5m×0.6m×1.0m的矩形空间(可以任何面朝下放置)。 4.6 整机功能检验 4.6.1 曳引检查

a.

在电源电压波动不大于2%工况下,用逐渐加载测定轿厢上、下行至与对重同一水平位置时的电流或电压测量法,检验电梯平衡系数应为40%~50%,测量表必须符合电动机供电的频率、电流、电压范围。

b.

电梯在行程上部范围内空载上行及行程下部范围125%额定载荷下行,分别停层3次以上,轿厢应被可靠地制停(下行不考核平层要求),在125%额定载荷以正常运行速度下行时,切断电动机与制动器供电,轿厢应被可靠制动。

c.

当对重支承在被其压缩的缓冲器上时,空载轿厢不能被曳引绳提升起。

d.

当轿厢面积不能限制载荷超过额定值时,再需用150%额定载荷做曳引静载检查,历时10min,曳引绳无打滑现象。

4.6.2 限速器安全钳联动试验

a.

额定速度大于0.63m/s及轿厢装有数套安全钳时应采用渐进式安全钳,其余可采用瞬时式安全钳;

b.

限速器与安全钳电气开关在联动试验中动作应可靠,且使曳引机立即制动;

c.

对瞬时式安全钳,轿厢应载有均匀分布的额定载荷,短接限速器与安全钳电气开关,轿内无人,并在机房操作下行检修速度时,人为让限速器动作。复验或定期检验时,各种安全钳均采用空轿厢在平层或检修速度下试验。

对渐进式安全钳,轿厢应载有均匀分布125%的额定载荷,短接限速器与安全钳电气开关,轿内无人。在机房操作平层或检修速度下行,人为让限速器动作。

以上试验轿厢应可靠制动,且在载荷试验后相对于原正常位置轿厢底倾斜度不超过5%。 4.6.3 缓冲试验

a.

蓄能型缓冲器仅适用于额定速度不大于1m/s的电梯,耗能型缓冲器可适用于各种速度的电梯;

b.

对耗能型缓冲器需进行复位试验,即轿厢在空载的情况下以检修速度下降将缓冲器全压缩,从轿厢开始离开缓冲器一瞬间起,直到缓冲器回复到原状,所需时间应不大于120s。 4.6.4 层门与轿门联锁试验

a.

在正常运行和轿厢未停止在开锁区域内,层门应不能打开;

b.

如果一个层门和轿门(在多扇门中任何一扇门)打开,电梯应不能正常启动或继续正常运行。 4.6.5 上下极限动作试验

设在井道上下两端的极限位置保护开关,它应在轿厢或对重接触缓冲器前起作用,并在缓冲器被压缩期间保持其动作状态。

4.6.6 安全开关动作试验

电梯以检修速度上下运行时,人为动作下列安全开关2次,电梯均应立即停止运行。

a.

安全窗开关,用打开安全窗试验(如设有安全窗);

b.

轿顶、底坑的紧急停止开关;

c.

限速器松绳开关。 4.6.7 运行试验

a.

轿厢分别以空载、50%额定载荷和额定载荷三种工况,并在通电持续率40%情况下,到达全行程范围,按120次/h,每天不少于8h,各起、制动运行1 000次,电梯应运行平稳、制动可靠、连续运行无故障。

b.

制动器温升不应超过60K,曳引机减速器油温升不超过60K,其温度不应超过85℃,电动机温升不超过GB 12974的规定。

c.

曳引机减速器,除蜗杆轴伸出一端渗漏油面积平均每小时不超过150cm2外,其余各处不得有渗漏油。

4.6.8 超载运行试验

断开超载控制电路,电梯在110%的额定载荷,通电持续率40%情况下,到达全行程范围。起、制动运行30次,电梯应能可靠地起动、运行和停止(平层不计),曳引机工作正常。 4.7 整机性能试验

4.7.1 乘客与病床电梯的机房噪声、轿厢内运行噪声与层、轿门开关过程的噪声应符合GB 10058规定要求。

4.7.2 平层准确度应符合GB 10058规定要求。

4.7.3 整机其他性能宜符合GB 10058有关规定要求。

5 验收规则

5.1 检验按表1规定项目进行。 5.2 判定规则

5.2.1 开关层、轿门过程噪声、平层准确度按GB 10058规定判定。 5.2.2

凡重要项目中任一项不合格,或一般项目中不合格超过8项,均判定为不合格。如重要项目均合格,一般项目中不合格不超过8项,则允许调整修复,并对原不合格项目及相关项目给予补检。凡最终重要项目全部合格,一般项目中不合格不超过3项,判定为合格,准于验收。判为安装不合格的电梯需全面修复,修复后再次报请验收。 5.3 交付检验验收合格后,参加验收的各方代表应在附录A(参考件)“电梯安装验收证书”上签字盖章后,方能生效。

表1 电梯安装验收检验项目分类表

序号项类检

目备注

1机房4.1.1条主电源开关要求☆

24.1.2条断、错相保护装置☆

34.1.3条敷线与接地要求

44.1.4条线管、槽敷设要求

54.1.5条控制柜、屏安装位置

64.1.6条楼板钢丝绳洞口要求

74.1.7条曳引机承重梁要求

84.1.8条旋转轮等涂色标志

94.1.9条旋转部件润滑要求

104.1.10条制动器松、合闸要求

114.1.11条绳、带轮铅垂度要求

124.1.12条限速器运转等要求☆

134.1.13条停电或故障应急措施☆

14井道4.2.1条导轨安装要求

154.2.2条导轨上端位置要求

164.2.3条导轨侧工作面直线度

174.2.4条导轨接头要求

184.2.5条导轨顶面间距

194.2.6条导轨固定要求

204.2.7条导轨下端支承地面要求

214.2.8条对重装置要求

224.2.9条限速器绳至导轨面偏差

234.2.10条轿厢与对重距离等要求

244.2.11条轿顶最小空间要求☆

254.2.12条井道照明要求

264.2.13条电缆支架安装要求

274.2.14条电缆安装要求

28轿厢4.3.1条轿顶反绳轮要求

294.3.2条轿底水平度

304.3.3条曳引绳头组合等要求

314.3.4条曳引绳要求

324.3.5条轿内操纵要求

334.3.6条轿顶停止开关☆

344.3.7条轿架限位碰铁安装要求

354.3.8条安全保护开关安装要求☆

36层站4.4.1条层站指示要求

374.4.2条层门地坎要求

384.4.3条层、轿门地坎间距

394.4.4条层门与地坎间隙

404.4.5条门刀与层门等间隙

414.4.6条门阻止力

424.4.7条门锁要求☆

434.4.8条层门外观要求

444.4.9条层门自动关闭装置

45底坑4.5.1条轿底与缓冲器等间距

464.5.2条缓冲器顶面水平高差

474.5.3条缓冲器柱塞铅垂度

484.5.4条底坑停止开关要求☆

494.5.5条轿底最小间距与空间

50整机功能4.6.1条曳引及平衡系数检查

514.6.2条限速器、安全钳联动试验☆

524.6.3条缓冲试验☆

534.6.4条层门与轿门联锁试验☆

544.6.5条上、下极限动作试验☆ 554.6.6条安全开关动作试验☆ 564.6.7条运行试验☆ 574.6.8条超载运行试验 584.7.1条噪声限值要求检验 594.7.2条平层准确度检验

第五篇:电梯安全使用规范

目的:规定电梯安全使用规范,以利相关人员遵循。

一、升降式客梯使用、保养规范:

(一)升降式客梯每日开启前,维修课必须对其例行检查(轿箱、自动门、开

关、应急电话),开启运行时,必须待设备运行一个周转后,看、听、

嗅其设备运行状况,确认正常方能离开。

(二)客梯在营业时间内设置为自动控制状态,方便顾客使用,以免长时间停

留在某一层面。

(三)客梯在营业时间内原则上严禁作为补货及运输卖场物品之用,只能作为

顾客上下通行用具。

(四)如卖场同时有两部客梯在同一处,卖场在营运高峰时迫不得已要作为补

货梯使用时,请将该客梯开在手动档上,并派专人控制。但要在各楼层

该台客梯门口贴POP告示顾客:“该客梯暂作运货,请顾客谅解,请乘坐

另一部客梯。"

(五)如卖场客梯只有一部供顾客使用,则绝对不允许在营业时间内用于其他

用途,只能服务于顾客,供顾客上下通行使用。

(六)营业中,由接待课长定时巡场检查客梯,如有异常声音等,应立即通知

维修人员检修,如人流拥挤,应派人维持秩序。

二、货梯使用、保养规范:

(一)货梯安全维护、保养责任由电梯供应商负责承担,分店维修课应在电梯

供应商指导下采取店内一般日常维护及保养。

(二)货梯内需安装防撞护栏,每层货梯口墙角必须安装防撞护角,与货梯接

口地坪处须安装铁板与货梯地坪衔接,并保持同一水平。

(三)货梯安全使用管理责任由客服部仓管课承担。

(四)货梯安全使用注意事项:

1、货梯每日启用前,维修课必须对其进行例行检查(轿箱、开关)。

开启运行时,必须待设备运行后,用看、听、嗅察看设备运行状况

,确认正常方能离开。

2、货梯醒目位置应有安全使用须知告示,货梯门处应有防撞护栏,地

坎沟槽内杂物每日至少清理二次。

3、货梯在运行时段,设置为人工控制状态,由客服部仓管课安排专人

操作,并设置看护人员排班表,一式二份,一份贴于货梯内,一份

叫仓管课留存,每周更换,以保证货梯正常运行。

4、乘货梯者严禁在桥箱内乱跳,倚靠、手推、撞踢桥箱门,严禁用手

或持物撬挖桥箱门,严禁向货梯桥箱门、高层门地坎沟槽内丢扔硬

物、杂物。在招呼货梯时,轻轻按下上行钮或下行钮,按钮灯亮后

不可反复按压。进出桥箱时应待高层门和桥箱门安全开 启、看清

桥箱正确位置后,再先出后进。

5、货梯是卖场货运大动脉,对在野蛮操作造成货梯故障或故意损坏者,

必须严加处罚。

6、货梯在运行时发现有异常状况,操作人员应立即停止使用并立即报

告课长、及时告知维修课检修,并在各货梯口悬挂POP告示:“货梯

修理中、暂勿使用”,维修课视情况或通知厂商人员检查修理。

7、货梯操作岗位的作息安排,由客服部仓管课负责。

三、客、货梯操作人员应持特种行业(电梯)操作证上岗。操作人员上岗证须复印